This study aim analyzes the accelerated completion duration of the Granola Housing of PT. Forkont Satria Nusantara, Palembang with crash program and fast track methods on the critical path that is sought using Critical Path Method (CPM), is then formulated in the linear program. where on crash program method using the alternative of adding four hours of work hours and implementing the system sh…