This research is backgrounded by the delay in the Flyover Gelumbang construction project, which recorded a negative deviation of 5.160% in the 37th week. The primary factors hindering work progress include adverse weather conditions and delays in the supply of materials such as granular, mini piles, and selected embankment. This delay caused the remaining work duration to swell to 112 days from…