This study evaluates the Fast Track method's effectiveness in optimizing time and cost management for the Air Serami Bridge replacement project in South Sumatra's Ogan Komering Ilir Regency. Through Precedence Diagram Method (PDM) and Microsoft Project analysis, the research demonstrates how parallel task execution with Start-to-Start scheduling reduced project duration by 4 days (2.22%) and sa…